COMPLETION OF ELECTRICAL CONDUIT AND BACKFILL - WEEK OF AUGUST 11, 2008

This week, Ryan Electric continued with electrical work and laid the electrical conduit to the new riser pole. The electrical conduits were inspected by the town, encased in concrete and backfill of the trenches started. The power will have to be turned off to the tennis courts for about two weeks. The contractor will try to minimize the time the power is down. We will install a sign at the courts to alert players so they can adjust their schedules accordingly. We apologize for any inconvenience. Next week will commence the pouring of the concrete foundation cap. The foundation cap will use 84 cubic yards (about 168 tons) of concrete. Conduit in trench alongside tennis courts - looking east

Conduit trench encased in concrete.

Conduit trench partially backfilled.

Conduit to teansformer location.

Conduit to tower.

Caisson to be filled with concrete.

Assembled anchor bolt cage.




To view some files, you may need AdobeTM Acrobat Reader. Get a FREE COPY at adobe.com.

© Copyright Porthsmouth Economic Development Committee - Sustainable Energy Subcomittee